UPDATE ON THE ROCKWOOD/STILLWOOD TRAFFIC CIRCLE

Here’s some new information on the status of the roundabout or traffic circle planned for the intersection of Rockwood Lane and Stillwood. The information is from Michael Gaudini, Policy Advisor to Council Member Leslie Pool:

“… the plan and designs for the traffic circle are done and the project is in utility review (to ensure that construction doesn’t accidentally damage water, electric, or another utility in the area).

After that, the project will go through permitting (the big element here is planning the traffic control, since construction will shut down that intersection).

Right now, Public Works is projecting that they’l have the permits this summer and their goal is to have the circle by the end of the summer. As always, these are just projections — heavy rains or other unforeseen issues could cause delays. But the project manager does know that this project has been in line for a while now and told me he is working hard to get this and other projects like it on the ground as quickly as he can.”

Thank you to Tomas Rodriguez for requesting this information.
Media Committee

UPDATE ON THE ROCKWOOD/STILLWOOD TRAFFIC CIRCLE